A widening project on Houston Street between Olive and Aspen avenues in Broken Arrow is close to completion, but a delay in the final concrete delivery has held up the remaining work. The shipment is now expected during Thanksgiving week, and the project will be finished once the concrete arrives and is installed.
The $4.6 million improvement is funded through the 2018 General Obligation Bond program. The city will post updates about the concrete delivery and installation on its website. For nearby businesses, the end of construction would bring relief after disruptions along the corridor.
Malid Al-Kouri, who has operated Jake's Cafe at Houston and Aspen for nearly 27 years, said the work has affected his business by about 30%. He is looking forward to its completion and said he had heard the project would be fully finished in December.
Elsewhere on Houston Street, construction between County Line Road and Old Highway 51 involves drainage improvements, new curbs and gutters along the south side, and new traffic signal poles. The poles are expected around Christmas. For now, traffic in both directions is using the north side of the street, with one lane available each way.
East of Midway, a full-depth reconstruction project has closed the west half of East Houston Street. Crews are replacing 1,000 feet of storm pipe in the drainage ditch on the north side, with new storm inlets expected soon. After completing the drainage work, crews will resume roadway base repairs at the project's east end and place the final asphalt layer.
Other work continues in northern and southern Broken Arrow. On County Line Road between Omaha and Albany streets, a contractor on an Oklahoma Department of Transportation project is widening both sides of the road for a new bridge. At the 9th Street and Washington Street intersection, crews are working on curbs and inlet connections, with completion anticipated around Christmas.
Recent maintenance on Lynn Lane between New Orleans and Washington streets included milling the pavement edges, adding 2 inches of asphalt and applying new striping. Washington Street between Lynn Lane and First Place also received milling and a 2-inch asphalt overlay. Multi-polymer striping remains to finish that project.
To help residents plan trips around construction and congestion, the city recently introduced a free interactive web map and app. The tools show construction areas, road closures and traffic slowdowns, along with closures associated with events such as parades and festivals.
Drivers can use the map to identify affected routes and consider detours before leaving. Its color-coded traffic display uses red, yellow and orange to indicate varying levels of congestion, including slower traffic and complete stops.